Kampala, Uganda | THE INDEPENDENT | Uganda Electricity Distribution Company Limited -UEDCL, says the Achwa 2 hydro-electric power station is ready to generate power for distribution to domestic and commercial end-users in northern Uganda. The 42 megawatts hydroelectric power plant is located in Angagura sub county along the Achwa river …
Read More »Gov’t fails to utilise UGX 4 trillion loan for electricty projects
Kampala, Uganda | THE INDEPENDENT | Government is yet to utilize over 4 trillion shillings meant for electricity projects throughout the country. According to the loan performance report of the Ministry of Energy and Minerals Development on loans under the sector, presented before the National Economy Committee in Parliament, …
Read More »MPs recommend additional ugx 334bn to boost electricity use
Kampala, Uganda | THE INDEPENDENT | The Natural Resources committee of parliament has recommended an extra Shillings 334 billion for electricity transmission, generation and distribution projects to utilize excess power. In its report to Parliament, the committee recommends that government allocates an additional Shillings 60 billion to the Rural Electrification Agency …
Read More »EAST AFRICAN BLACKOUT: Uganda disconnected from Kenyan grid
Kampala, Uganda | THE INDEPENDENT | Uganda Electricity Generation Company Limited (UEGCL) has confirmed that the cause of the power outage that has left several areas in East Africa in a blackout, was in Kenya. Corporate Affairs Manager UEGCL Simon Kasyate told Uganda’s Daily Monitor that they had established the cause …
Read More »Karuma dam construction reaches 71%
Kampala, Uganda | JULIUS BUSINGE | Physical progress of works (civil, hydro-mechanical and electro-mechanical) of the construction of the 600MW Karuma hydro-power dam is now at 71% completion rate ahead of official commissioning in December next year. The dam, which is constructed under the ground, is costing the government of Uganda …
Read More »Muhakanizi, Isabalija ‘fight’ sparks Shs 30bn UEGCL audit
Finance PS controls government purse, but new Energy PS has Museveni’s ear A stealth fight is brewing between new Energy Ministry Permanent Secretary, Stephen Isabalija, and veteran Secretary to the treasury, Keith Muhakanizi, with insiders saying it threatens to hurt implementation of government projects worth billions of shillings, if not …
Read More »Kiggundu moves to fix Karuma dam cracks
Museveni’s new team at Energy ministry grills Chinese contractors The midday sun is beating down hard at Karuma; site of what will be Uganda’s biggest electricity dam; the 600MW Hydropower Dam under construction. Gargantuan tower cranes stand several feet high, hoisting thick blocks of pre-fabricated concrete and iron bars atop …